Free PMI PfMP Exam Questions

Become PMI Certified with updated PfMP exam questions and correct answers

Page:    1 / 100      
Total 500 Questions | Updated On: Jan 10, 2025
Add To Cart
Question 1

Assume you are helping the Portfolio Review Board select and implement the portfolio with the best alignment to strategy as you work to create a list for to be considered for prioritization. One possible component on the surface does not seem to be one that is profitable, but you believe that over time changes will occur that will make it cost/beneficial to pursue. This means you are using:


Answer: D
Question 2

When initiating portfolio components and terminating other, you come up with updates to budget, funding and resources allocations. Where should these updates be recorded?


Answer: C
Question 3

You have a portfolio component that is using earned value analysis. It is at the 15% point of completion, and it
is evident that it cannot be completed as planned. Adding resources will not solve the problem, and at the last
Portfolio Review Board meeting, the Board members decided to terminate this component based on its various
risks. They then decided the resources allocated to this component could be transferred to other portfolio
components enhancing their early completion and avoiding risks from competitors. As the portfolio manager,
you:


Answer: B
Question 4

You have been managing a complex portfolio for the banking industry and it is sought to be the shifting to the
top-notch digital banking era for one of the major international banks. You know you will have changes along
the lifecycle and you plan to manage them correctly in order to maintain alignment and correct execution. If
you need to reflect changes based on cost, requirements, and schedule. To which of the following section in
the portfolio management plan will you refer?


Answer: D
Question 5

Communication is one of the largest activities that the portfolio manager does along the portfolio lifecycle. As
an experienced portfolio manager, you know that communication and information needs vary between
portfolios, programs and projects. How do you define the difference in those three levels of Project
Management?


Answer: B
Page:    1 / 100      
Total 500 Questions | Updated On: Jan 10, 2025
Add To Cart

© Copyrights DumpsCertify 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsCertify.