Free PMI PMI-SP Exam Questions

Become PMI Certified with updated PMI-SP exam questions and correct answers

Page:    1 / 65      
Total 325 Questions | Updated On: Feb 18, 2025
Add To Cart
Question 1

Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during analysis? Each correct answer represents a complete solution. Choose three. 


Answer: B,C,D
Question 2

You are the project manager for your organization. Maagement has asked you for this current project. You use the critical chain method to create the project network diagram rather than the more traditional critical path method. What is the critical chain method?


Answer: C
Question 3

You are the project manager for the NQQ Project for your organization. You and the project team are creating the activity list for the NQQ Project. You have instructed the project team members that they should include an activity identifier and a scope of work description for each activity in the activity list. Why is this information needed? 


Answer: C
Question 4

Nancy is the project manager of the JJJ Project. This project has recently been approved by the project customer as complete so Nancy must now finalize the administrative closure. Nancy needs to create the final project report to report the successes and failures in the project. Who should Nancy deliver this final project report to if she is participating in a projectized structure?


Answer: C
Question 5

You are the project manager for your organization. Your current project has a schedule variance of -$37,500 and a schedule performance index of 0.94. What do these values mean in regard to project performance? 


Answer: D
Page:    1 / 65      
Total 325 Questions | Updated On: Feb 18, 2025
Add To Cart

© Copyrights DumpsCertify 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsCertify.