Free PMI PMI-RMP Exam Questions

Become PMI Certified with updated PMI-RMP exam questions and correct answers

Page:    1 / 89      
Total 445 Questions | Updated On: Mar 26, 2025
Add To Cart
Question 1

Which of the following will ultimately determine risk thresholds?


Answer: B
Question 2

In what portion of a project are risk and opportunities greatest and require intense planning and anticipation of risk events?


Answer: C
Question 3

Mark works as a project manager for TechSoft Inc. Mark, the project team, and the key project stakeholders have completed a round of qualitative risk analysis. He needs to update the risk register with his findings so that he can communicate the risk results to the project stakeholders – including management. Mark will need to update all of the following information except for which one?


Answer: A
Question 4

You work as a project manager for TechSoft Inc. You are working with the project stakeholders on the qualitative risk analysis process in your project. You have used all the tools to the qualitative risk analysis process in your project. Which of the following techniques is NOT used as a tool in qualitative risk analysis process?  


Answer: C
Question 5

Thomas is a key stakeholder in your project. Thomas has requested several changes to the project scope for the project you are managing. Upon review of the proposed changes, you have discovered that these new requirements are laden with risks and you recommend to the change control board that the changes be excluded from the project scope. The change control board agrees with you. What component of the change control system communicates the approval or denial of a proposed change request? 


Answer: C
Page:    1 / 89      
Total 445 Questions | Updated On: Mar 26, 2025
Add To Cart

© Copyrights DumpsCertify 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsCertify.