Free PMI PMI-CP Exam Questions

Become PMI Certified with updated PMI-CP exam questions and correct answers

Page:    1 / 12      
Total 60 Questions | Updated On: Nov 11, 2024
Add To Cart
Question 1

A construction professional is leading the construction of a new hospital. The project is halfway through its scheduled time frame. The construction professional monitors the scope along with other project constraints, and thinks that, overall, the project seems to be on track. However, some key stakeholders are concerned about potential cost overruns.

What can the construction professional do to address the stakeholders' concerns?


Answer: B
Question 2

An organization kicked off a large construction project of a three-year duration. Due to its importance to the national economy, the government obliged the organization to submit a monthly report including progress description, financial status, change orders, and forecasting measurements. After creating the first report, the organization found that it takes too much time to manually generate the report and therefore decided to leverage technology to meet the government requirements.

What technologies could the organization use? (Select two)


Answer: A,B
Question 3

A construction professional decides to use the PDRI tool throughout the Front End Planning (FEP) process. The construction professional defined four assessment points: after the feasibility study, after the concept phase, during the detailed scope phase, and at the end of the FEP phase.

How will the PDRI score typically evolve through these assessment points?


Answer: B
Question 4

An organization is running a construction megaproject with over 100 interfaces. As it faced some issues in IM implementation, the organization requested the advice of a senior construction professional. After assessing the existing IM implementation, the construction professional recommended the organization to set up a single centralized document to easily review the status of all Interface Agreements (IA).

What document does the construction professional refer to?


Answer: C
Question 5

A senior construction professional works on a nuclear power plant which will be planned and executed using the Advanced work packaging (AWP) approach. After the definition of construction work areas (CWAs), the construction professional moved on to the preparation for the workface planning phase. One of the project planning team wondered about the relationship between the Engineering Work Packages (EWP), the Construction Work Packages (CWP), and the Installation Work Packages (IWP).

What should the construction professional’s answer be? (Select two)


Answer: A,D
Page:    1 / 12      
Total 60 Questions | Updated On: Nov 11, 2024
Add To Cart

© Copyrights DumpsCertify 2024. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsCertify.