Question 1

During sprint planning the product owner wants the team to prioritize and deliver a number of features which have the highest business value. Due to technical dependencies, the team does not agree with the prioritization.
What should the project leader do?


Answer: C
Question 2

During an iteration planning meeting, the team suggests changes to add product vale that will require extra work and impact the schedule.

What should the agile project leader do?


Answer: D
Question 3

What is the first thing an agile development team should do when planning an iteration?


Answer: C
Question 4

During a retrospective, a team member claims that a specific set of documentation that is continuously updated during iterations is not being used by any stakeholder. What should the team do?


Answer: D
Question 5

After three iterations, it is identified that a project's underlying security structure architecture is unstable. While there is a technical solution, all work to date is flawed. This will impact several future business service offerings.
What should the product owner do to resolve this?


Answer: B
Page:    1 / 65      
Total 325 Questions | Updated On: Jan 07, 2025
Add To Cart

© Copyrights DumpsCertify 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsCertify.