Test Management
You are managing the system testing for a SOA based system. The integrated system
consists of several subsystems:
- a SOA middleware
- a CRM (Customer Relationship Management) system
- a BRM (Billing and Revenue Management) system
- a SMS (Subscriber Management System) system
and you performed a risk analysis based on these subsystems.
At the end of the scheduled period for test execution you produce a first classical report
based on the traditional metrics of testing. Test pass/fail status and bug status
(open/resolved) That table provides you a distorted picture of the quality risk, because
there is no indication of the risk level of the failed tests, the tests not run, or the open bugs.
Thus, you produce the following table to solve this distortion issue:
In the table above, where you have introduced the concept of risk weighting, the highest
risk test or bug report has a score of 1, while the lowest risk test or bug report has a score
of 0.04.
Which of the following subsystems, based on the risk scores of the table, is most risky?
Number of correct responses: 1
K4 3 credits