Test Management
You are the Test Manager of a new project aimed at developing a software system that
must be certified at level B of the DO-178B standard. The project will follow a V-Model
software development life cycle and it will have four formal levels of testing: component,
integration, system and acceptance testing.
You must produce the test plan documentation for this project by providing an adequate
coordination across the four levels of testing in order to assure auditability.
Which of the following answers would you expect to best describe how to organize the test
plan?
Number of correct responses: 1
K3 2 credits