Free CIMA CIMAPRO19-P01-1-ENG Exam Questions

Become CIMA Certified with updated CIMAPRO19-P01-1-ENG exam questions and correct answers

Page:    1 / 53      
Total 261 Questions | Updated On: Nov 13, 2024
Add To Cart
Question 1

A company's budget for the next period shows that it would breakeven at sales revenue of $800,000 and fixed costs of $320,000.
The sales revenue needed to achieve a profit of $200,000 in the next period would be:


Answer: D
Question 2

Two products being produced by a company require the same material which is limited to 2,600 kgs.

72

What is the optimal production plan?


Answer: A
Question 3

Which TWO of the following statements are true for obtaining a reliable forecast from a time series?


Answer: B,C
Question 4

RFT, an engineering company, has been asked to provide a quotation for a contract to build a new engine. The potential customer is not a current customer of RFT, but the directors of RFT are keen to try and win the contract as they believe that this may lead to more contracts in the future. As a result, they intend pricing the contract using relevant costs. The following information has been obtained from a two-hour meeting that the Production Director of RFT had with the potential customer. The Production Director is paid an annual salary equivalent to $1,200 per 8-hour day. 110 square meters of material A will be required. This is a material that is regularly used by RFT and there are 200 square meters currently in inventory. These were bought at a cost of $12 per square meter. They have a resale value of $10.50 per square meter and their current replacement cost is $12.50 per square meter. 30 liters of material B will be required. This material will have to be purchased for the contract because it is not otherwise used by RFT. The minimum order quantity from the supplier is 40 liters at a cost of $9 per liter. RFT does not expect to have any use for any of this material that remains after this contract is completed. 60 components will be required. These will be purchased from HY. The purchase price is $50 per component. A total of 235 direct labour hours will be required. The current wage rate for the appropriate grade of direct labour is $11 per hour. Currently RFT has 75 direct labour hours of spare capacity at this grade that is being paid under a guaranteed wage agreement. The additional hours would need to be obtained by either (i) overtime at a total cost of $14 per hour; or (ii) recruiting temporary staff at a cost of $12 per hour. However, if temporary staff are used they will not be as experienced as RFT's existing workers and will require 10 hours supervision by an existing supervisor who would be paid overtime at a cost of $18 per hour for this work. 25 machine hours will be required. The machine to be used is already leased for a weekly leasing cost of $600. It has a capacity of 40 hours per week. The machine has sufficient available capacity for the contract to be completed. The variable running cost of the machine is $7 per hour. The company absorbs its fixed overhead costs using an absorption rate of $20 per direct labour hour.
Select ALL the true statements.


Answer: A,C,D
Question 5

The standard production cost of making a product is as follows:

3

What is the fixed production overhead capacity variance?


Answer: B
Page:    1 / 53      
Total 261 Questions | Updated On: Nov 13, 2024
Add To Cart

© Copyrights DumpsCertify 2024. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsCertify.