Free CIMA CIMAPRO19-P01-1-ENG Exam Questions

Become CIMA Certified with updated CIMAPRO19-P01-1-ENG exam questions and correct answers

Page:    1 / 53      
Total 261 Questions | Updated On: Dec 08, 2025
Add To Cart
Question 1

Christian the management accountant at a car manufacturer has been given a list of costs that have been incurred due to accidents and errors either occurring or being prevented.
Which of the following are examples of non-conformance costs? Select ALL that apply.


Answer: A,B,C
Question 2

A medium-sized manufacturing company, which operates in the electronics industry, has employed a firm of consultants to carry out a review of the company's planning and control systems. The company presently uses a traditional incremental budgeting system and the inventory management system is based on economic order quantities (EOQ) and reorder levels. The company's normal production patterns have changed significantly over the previous few years as a result of increasing demand for customized products. This has resulted in shorter production runs and difficulties with production and resource planning. The consultants have recommended the implementation of activity based budgeting and a manufacturing resource planning system to improve planning and resource management.
What are the benefits for the company that could occur following the introduction of an activity based budgeting system?
Select ALL the correct answers.


Answer: A,B,C
Question 3

THS produces two products from different combinations of the same resources. Details of the products are shown below:

73
Identify, using graphical linear programming, the optimal production plan for products E and R to maximize THS's profit in the month.


Answer: D
Question 4

A company accountant is trying to determine the optimum production plan for the period using linear programming.
The accountant has correctly formulated the linear programming problem as follows:
Variables (products): x and y
Objective function: Maximise contribution, C = 10x + 15y
Material constraint: 4x + 6y 500 (kg)
Labour constraint: x + 2y 350 (hours)
Machine constraint: 10x + 4y 1,500 (hours)
x constraint: 50 x 200
y constraint: y 0
Which of the following statements is true?


Answer: D
Question 5

RFT, an engineering company, has been asked to provide a quotation for a contract to build a new engine. The potential customer is not a current customer of RFT, but the directors of RFT are keen to try and win the contract as they believe that this may lead to more contracts in the future. As a result, they intend pricing the contract using relevant costs. The following information has been obtained from a two-hour meeting that the Production Director of RFT had with the potential customer. The Production Director is paid an annual salary equivalent to $1,200 per 8-hour day. 110 square meters of material A will be required. This is a material that is regularly used by RFT and there are 200 square meters currently in inventory. These were bought at a cost of $12 per square meter. They have a resale value of $10.50 per square meter and their current replacement cost is $12.50 per square meter. 30 liters of material B will be required. This material will have to be purchased for the contract because it is not otherwise used by RFT. The minimum order quantity from the supplier is 40 liters at a cost of $9 per liter. RFT does not expect to have any use for any of this material that remains after this contract is completed. 60 components will be required. These will be purchased from HY. The purchase price is $50 per component. A total of 235 direct labour hours will be required. The current wage rate for the appropriate grade of direct labour is $11 per hour. Currently RFT has 75 direct labour hours of spare capacity at this grade that is being paid under a guaranteed wage agreement. The additional hours would need to be obtained by either (i) overtime at a total cost of $14 per hour; or (ii) recruiting temporary staff at a cost of $12 per hour. However, if temporary staff are used they will not be as experienced as RFT's existing workers and will require 10 hours supervision by an existing supervisor who would be paid overtime at a cost of $18 per hour for this work. 25 machine hours will be required. The machine to be used is already leased for a weekly leasing cost of $600. It has a capacity of 40 hours per week. The machine has sufficient available capacity for the contract to be completed. The variable running cost of the machine is $7 per hour. The company absorbs its fixed overhead costs using an absorption rate of $20 per direct labour hour.
Select ALL the true statements.


Answer: A,C,D
Page:    1 / 53      
Total 261 Questions | Updated On: Dec 08, 2025
Add To Cart

© Copyrights DumpsCertify 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsCertify.