Free CIMA CIMAPRA19-P03-1-ENG Exam Questions

Become CIMA Certified with updated CIMAPRA19-P03-1-ENG exam questions and correct answers

Page:    1 / 56      
Total 276 Questions | Updated On: Apr 02, 2026
Add To Cart
Question 1

Which TWO of the following scenarios should be considered in strategic scenario planning by a publishing company that specialises in academic textbooks?


Answer: B,C
Question 2

A has an opportunity to invest $90,000 in a project that is expected to generate annual cash inflows of $60,000 for each of the next three years. The project's beta coefficient implies a discount rate of 12% for this project, based on a risk-free rate of return of 3%.
A is prepared to forego the expected cash flows from this project in return for a guaranteed payment of $50,000 at the end of year 1, $42,000 at the end of year 2 and $30,000 at the end of year 3.
What is the certainty equivalent value of this opportunity to A?


Answer: B
Question 3

A capital investment project shows a NPV of 3,450 at a discounted rate of 8% and an NPV of 1,210 at a discounted rate of 9%.
Whatistheinternal rate ofreturn?


Answer: D
Question 4

The internal audit department has just completed an investigation into the HR department's procedures relating to new staff appointments The head of HR is unhappy with the draft report prepared by the lead internal auditor The report lists several cases in which appointments were made despite the fact that one or more of the entity's formal procedures were not followed
The head of HR has complained that the internal auditor's comments do not allow for the fact that the HR department's staff members are often very busy and do not always have time to conduct every check.
The internal auditor's comments also reflect a failure to complete documents None of the omissions have led to the appointment of an unsuitable member of staff
Which TWO of the following statements reflect an appropriate response by the board of directors to this report?


Answer: A,C
Question 5

Having carried out a full capital appraisal for a construction project, HCompanyhasapproved the project with initial outflows of $6,000,000 anda net present value of $1,200,000.
The implementation phase has been commenced with 25% of the costs already committed.However whenthe ground was opened, an underground waterway was revealedwhich will need to be diverted if the project is to proceed. Work to carry out this diversion has been estimated at $1,300,000.
Which of the following factors will define whether the project should go ahead or not?


Answer: A,D
Page:    1 / 56      
Total 276 Questions | Updated On: Apr 02, 2026
Add To Cart

© Copyrights DumpsCertify 2026. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsCertify.