Question 1

Your organization has a requirement to retrieve the value of the cost center segment based on the department.
Which source can you use while defining the account rule to achieve this requirement?


Answer: A
Question 2

Your organization performs revenue recognition based on the Labor and Non-labor Burden schedule types. Identify the setup required to enable this kind of revenue recognition. (Choose the best answer.)


Answer: B
Question 3

Your customer has different accounting and project accounting periods, and sometimes enters invoices with an invoice date in the open project accounting and closed accounting periods. Which two statements are true about how project accounting and accounting dates will be populated in such invoices? (Choose two.)


Answer: A,B
Question 4

You have defined two expenditure types but they are not available for selection when you enter an expenditure batch. What is the reason for this problem? 


Answer: C
Question 5

You are managing a project based on a Waterfall model. You define a project and a project plan in Oracle Project Management with tasks and subtasks applicable to each of the phases of the project: Initiation, Discovery, Design, Build, Test, and Deploy. As a project manager, you want to define deliverables for your project requirements that are elucidated during the Discovery phase of your project. You now want to understand how the inheritance between requirements, tasks, and deliverables works.
Which two are correct statements in this scenario? (Choose two.)


Answer: A,D
Page:    1 / 27      
Total 132 Questions | Updated On: Feb 18, 2025
Add To Cart

© Copyrights DumpsCertify 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsCertify.